snuffy
03-27-2008, 08:15 AM
Thursday, March 27, 2008
University construction in various stages of completion
The North Classroom Building on Hall of Fame and Monroe Streets is scheduled to be completed in November and ready for classes in spring 2009. It is one of many ongoing projects on and around campus slated for completion in the next two years.
By PETER WOOD
Staff Writer
Old Central:
TAP Architecture and CMS Willowbrook are working on Old Central.
The foundation work for the Old Central building is complete. Efforts have moved to the renovation stage of the project. The companies expect to finished the development February 2009.
Murray Hall:
PSA Dewberry and CMS Willowbrook are working on Murray Hall.
The construction companies have completed internal demolition and asbestos removal. The rebuilding, as well as external work to improve drainage, is well under way. Work on a new auditorium in the courtyard is will begin soon. The companies expect to complete the project June 2009.
Donald W. Reynolds School of Architecture Building:
Studio Architecture and Boldt Construction are working on this project.
Internal demolition in the existing building is complete; Work on new wings on the east and west sides of the building has begun. Expected completion of this project is April 2009.
Interdisciplinary Science Research Building (located next to the Physical Science building):
Rees Associates Architects, Cannon Design and Flintco Constructive Solutions are working on this project.
This area of construction is in its early stages of development, including the foundation work. In the construction process they have erected a crane, and expect the area to be ready for use in May 2010.
North Classroom Building:
LWPB Architecture and Manhattan Construction Company are working on this building.
The steel frame for the new building is complete. The topping out ceremony was Feb. 21 when the companies installed the last piece. They expect to complete the classroom building November and have it ready for classes in the spring 2009 semester.
Multi-modal Transportation Terminal (the bus terminal closer to Hall of Fame) and Monroe Street Parking Garage:
Construction of the garage foundations is complete and installation of precast concrete floors and wall panels is under way.
The foundation for the terminal building is complete, and the frame for the building is nearly done. The parking garage will be ready for use August 2008 and the terminal will be completed about September.
Oklahoma Animal Disease Diagnostic Laboratory (expansion of existing building at west end of Farm Road):
Studio Architects and Flintco Constructive Solutions are working on this project. Next to the Motor Hub on Farm Road, the work on this site will start soon. The project will be completed in the summer of 2009.
Information courtesy of Nigel Jones, Long Range Facilities Planning Office
http://ocolly.com/2008/03/27/university-construction-in-various-stages-of-completion/
University construction in various stages of completion
The North Classroom Building on Hall of Fame and Monroe Streets is scheduled to be completed in November and ready for classes in spring 2009. It is one of many ongoing projects on and around campus slated for completion in the next two years.
By PETER WOOD
Staff Writer
Old Central:
TAP Architecture and CMS Willowbrook are working on Old Central.
The foundation work for the Old Central building is complete. Efforts have moved to the renovation stage of the project. The companies expect to finished the development February 2009.
Murray Hall:
PSA Dewberry and CMS Willowbrook are working on Murray Hall.
The construction companies have completed internal demolition and asbestos removal. The rebuilding, as well as external work to improve drainage, is well under way. Work on a new auditorium in the courtyard is will begin soon. The companies expect to complete the project June 2009.
Donald W. Reynolds School of Architecture Building:
Studio Architecture and Boldt Construction are working on this project.
Internal demolition in the existing building is complete; Work on new wings on the east and west sides of the building has begun. Expected completion of this project is April 2009.
Interdisciplinary Science Research Building (located next to the Physical Science building):
Rees Associates Architects, Cannon Design and Flintco Constructive Solutions are working on this project.
This area of construction is in its early stages of development, including the foundation work. In the construction process they have erected a crane, and expect the area to be ready for use in May 2010.
North Classroom Building:
LWPB Architecture and Manhattan Construction Company are working on this building.
The steel frame for the new building is complete. The topping out ceremony was Feb. 21 when the companies installed the last piece. They expect to complete the classroom building November and have it ready for classes in the spring 2009 semester.
Multi-modal Transportation Terminal (the bus terminal closer to Hall of Fame) and Monroe Street Parking Garage:
Construction of the garage foundations is complete and installation of precast concrete floors and wall panels is under way.
The foundation for the terminal building is complete, and the frame for the building is nearly done. The parking garage will be ready for use August 2008 and the terminal will be completed about September.
Oklahoma Animal Disease Diagnostic Laboratory (expansion of existing building at west end of Farm Road):
Studio Architects and Flintco Constructive Solutions are working on this project. Next to the Motor Hub on Farm Road, the work on this site will start soon. The project will be completed in the summer of 2009.
Information courtesy of Nigel Jones, Long Range Facilities Planning Office
http://ocolly.com/2008/03/27/university-construction-in-various-stages-of-completion/